Three campuses, 17,256 worker vehicles, one set of two-lane roads. What happens if nothing is done. What flaggers do. What a timed signal does. What a shuttle system requires, and whether any of them actually clear the roads by the start of shift.

17,256Worker vehicles, three campuses
600 / hourUnsignalized mouth, one car at a time
9.6 hoursTo empty one driveway at that rate
9.1 milesCR 609 from SR 714 to Warfield
The Load

What Has to Move

Each campus is sized at 6,500 people. At the National Household Travel Survey work-trip rate of 1.13 people per vehicle, that is 5,752 vehicles at each driveway and 17,256 across the three. Add about 1,080 truck trips a day in the concrete peak. The crews do not live in the village. St. Lucie and the West Palm Beach area supply about 35 percent each. Okeechobee supplies about 20 percent. Stuart is a thin market at about 10 percent.

Every one of those trips ends at one of three mouths. Silver Fox enters on Silver Fox Lane off Warfield. Growler enters off Warfield. FPL / Tesoro enters on Kanner. The roads are two lanes. None of the mouths has a signal. A vehicle on the driveway side turns in behind the car ahead of it. A vehicle on the far side has to cross the opposing lane. That crossing is the limit.

The working rate for an unsignalized crossing, one vehicle at a time, is one every 6 seconds. That is 600 vehicles an hour. At that rate a single driveway takes 9 hours and 35 minutes to empty. The first car has to be in line at 10:25 the night before to be parked by 8:00 AM. The last car from a 4:00 PM release is still on the road past 1:30 AM.

Storage is not capacity

CR 609 from SR 714 to Warfield is 9.1 miles, 48,048 feet. A 15-foot car with a 3-foot gap takes 18 feet. That stretch holds about 2,669 cars in one lane. The 609 share is about 2,014 vehicles, roughly 6.9 miles of that road. The cars fit. The mouth cannot empty them. At 600 an hour, those 2,014 vehicles take 3 hours and 20 minutes just to turn onto Warfield, before they join the line at Silver Fox or Growler.

Demonstration

The Same Roads, Four Ways

This is the same map and the same queue model as the traffic page. Pick a scenario. The mouth rate changes. The roads do not. Blues are worker vehicles. Orange are trucks. Green is traffic already on the road. In the shuttle case the blues become buses and the private cars are off the two-lane.

05:00:00

Nothing done. One vehicle every 6 seconds, 600 an hour. The line does not clear by 8:00.

Silver FoxGrowlerFPL / Tesoro SR 710 / WarfieldSR 76 / KannerSR 714CR 609Silver Fox Ln 5:00 AM early birds. Due on site at 8:00. At 8:00 the line is still off this map.
● Worker vehicle ● Truck ● Traffic already on the road ● Shuttle bus

Early birds start at 5:00 AM. Due on site at 8:00.

Scenario 1

If Nothing Is Done

No signal. No flagger. No stagger. No off-site lot. Each campus calls its crews for an 8:00 AM start and releases them at 4:00 PM. The three peaks land together because the projects are moving through approval at the same speed.

MeasureResult
Mouth rate600 vehicles an hour, far-side crossing
One driveway, workers only5,752 ÷ 600 = 9.6 hours
First car in line for 8:00 AM10:25 PM the night before
Last car out after 4:00 PMPast 1:30 AM
609 share, turn onto Warfield2,014 ÷ 600 = 3.4 hours
Line length on 609About 6.9 miles of the 9.1 available

Trip time for a worker is not the drive. It is the drive plus the queue. A car that reaches the back of a 6.9-mile line on 609 at 5:00 AM is still on 609 at 8:00 AM. It has not turned onto Warfield. It has not reached the gate. The shift has started without it.

Strengths

None for the road. No cost to the applicant. No new infrastructure. The site plan can be drawn as if the cars disappear at the property line.

Weaknesses

The line never clears. Local traffic, including EMS, sits in the same lane. The three gas stations, the grocery, and the convenience stores are on the other side of the queue. A crash or a stalled truck anywhere in the 9 miles stops everything behind it.

Does it work

No. The demand at one mouth is 9.6 hours of flow. The morning window is about 3 hours. The arithmetic does not close. The cars are still on the road when the shift is supposed to start, and they are still on the road when it ends.

Scenario 2

Staggered Arrivals

The crews do not all reach the line at 5:00. They join it across the morning. Some are early. Some cut it close to 8:00. The line builds and drains at the same time instead of starting full. On the map, pick Staggered. The road is nearly empty at 5:00. Cars appear as the clock runs.

Spread 5,752 vehicles over three hours and the arrival rate is about 1,900 an hour. The mouth is still 600. The line grows, just more slowly than if everyone were already there. By 8:00 the queue is shorter than the do-nothing case. It has not disappeared.

MeasureResult
Arrival window5:00 AM to 8:00 AM
Arrival rate, one driveway5,752 ÷ 3 hours ≈ 1,900 an hour
Mouth rateStill 600 an hour
Net buildAbout 1,300 vehicles an hour added to the line
Queue at 8:00, one drivewayOn the order of 4,000 vehicles still waiting
609 share over 3 hoursAbout 670 an hour arriving, 600 leaving. Nearly balanced on that feeder alone.

Trip time depends on when you arrive. A car that joins at 5:15 may clear before 8:00. A car that joins at 7:30 is behind everyone who came earlier and is still in line at the start of shift. The average wait drops. The late arrivals do not.

Strengths

No construction. No fleet. Matches how crews actually leave home. Cuts the overnight line. On a single feeder like 609, the arrival rate can come close to the mouth rate, so that stretch does not fill the way it does when everyone is already there.

Weaknesses

It is voluntary unless the start times are assigned. If the job starts at 8:00, people still bunch toward 8:00. Three campuses with the same start hour stagger into the same window. The mouth is unchanged, so the surplus still stacks. It does not help the evening release at all.

Does it work

Better than everyone at once. Not enough on its own. The arrival rate is still about three times the mouth. The line at 8:00 is shorter, not gone. Stagger plus a signal, or stagger plus a shuttle, is a different problem. Stagger alone leaves cars on the road at the start of shift.

Scenario 3

Flag Men

A flagger at each mouth, and at the 609 and Kanner turns onto Warfield, stops the opposing lane and waves the queue through. This is manual gap creation. It removes the wait for a natural break in traffic. It does not add a lane, and it does not add a second mouth.

A practiced flagger running a single-lane crossing can move traffic faster than an unsignalized gap, because the opposing lane is held instead of flowing. A reasonable working rate is about 900 vehicles an hour, one car every 4 seconds, with the flagger alternating directions. That is an improvement. It is not a doubling.

MeasureResult
Mouth rate with flaggerAbout 900 vehicles an hour
One driveway5,752 ÷ 900 = 6.4 hours
First car in line for 8:00 AMAbout 1:35 AM
609 share2,014 ÷ 900 = 2.2 hours
Flagger shift to cover the queue6 to 10 hours at each point

Trip time improves on the crossing itself. A car that waited 6 seconds for a gap now waits for the flagger's cycle, which can be shorter if the opposing volume is low. On these roads in the arrival hour, the opposing volume is the other campuses. The flagger is stopping one work line to move another. The net gain is real but modest.

Strengths

No construction. Can be stood up in a day. Flexible. A flagger can favor the ambulance, the school bus, or a resident in a way a fixed signal does not. Cheap relative to a signal or a lot.

Weaknesses

Human limit. A flagger running a 6-hour queue makes mistakes. Fatigue, shift changes, and weather all cut the rate. Three campuses need flaggers at three mouths plus the feeder turns, all at once, all morning and all evening. It does not shorten the line on 609. It only drains it faster, and 6.4 hours still does not fit in a morning.

Does it work

Partly. It is better than nothing. It does not solve it. The first car is still in line in the middle of the night. The 609 queue still takes more than two hours to turn. A flagger plan without a stagger or a shuttle leaves the roads blocked through the start of shift.

Scenario 4

Timed Lights

A temporary signal at each mouth, and at the 609 and Kanner junctions, gives each direction a fixed green. The far-side cars no longer hunt for a gap. The rate rises because the opposing lane is stopped on a clock instead of by eye.

A simple two-phase temporary signal on a two-lane approach can move about 1,000 to 1,200 vehicles an hour through one movement, depending on the cycle and the share of trucks. Use 1,100 as the working number. That is nearly double the unsignalized rate.

MeasureResult
Mouth rate with signalAbout 1,100 vehicles an hour
One driveway5,752 ÷ 1,100 = 5.2 hours
First car in line for 8:00 AMAbout 2:45 AM
609 share2,014 ÷ 1,100 = 1.8 hours
Points that need a signalThree mouths, plus 609 at Warfield, plus Kanner at Warfield

Trip time at the crossing drops. A car that sat through a long gap wait now gets a green every cycle. If the cycle is 60 to 90 seconds and the work movement gets half of it, the wait at the line is bounded. The line itself is not. A 6.9-mile queue on 609 still has to creep forward one car at a time until it reaches the signal. The signal drains it faster. It does not make the back of the line move until the front has moved.

Strengths

Consistent. Does not fatigue. Can be timed to give the through lane a guaranteed green so local traffic and EMS are not trapped for the whole morning. Higher rate than a flagger. Runs the same at 5:00 AM and at 9:00 AM.

Weaknesses

Cost, power, and time to install. Five signals, not one. A fixed timing plan that favors the work line punishes the through traffic. A plan that favors through traffic slows the work line back toward the flagger rate. It still leaves a 5-hour drain at each mouth. The first car is still in line before 3:00 AM. And a signal at the mouth does nothing for a stall or a crash in the middle of the 9 miles.

Does it work

Better than flaggers. Still no. 5.2 hours at the mouth does not fit between a reasonable arrival and an 8:00 AM start unless the crews are on the road in the middle of the night. The signals make the crossing fairer and faster. They do not make the volume fit the clock.

Scenario 5

The Shuttle

The shuttle does not remove the trip. It moves where the car parks. The worker drives to a lot on a high-capacity road, leaves the car, and rides a bus the rest of the way. The two-lane roads carry buses instead of 17,256 private vehicles. This is the only option in this set that changes the number of vehicles on 609, Warfield, and Kanner.

How many people, how many buses

6,500 people per campus is 19,500 people. A standard transit or coach bus carries about 45 passengers. That is 434 bus trips to deliver everyone, and 434 to take them home. They do not move in one wave. Over a two-hour arrival window that is about 220 buses an hour across all lots, or about 70 an hour if the three campuses stagger their starts by an hour.

A bus cycle is the drive from the lot to the gate, the unload, the return, and the reload. From a lot at the I-95 / SR 714 interchange to the Warfield gates is on the order of 20 to 30 minutes each way in clear traffic, longer if the bus sits in what remains of the queue. A working cycle is about 60 to 75 minutes. To hold 70 buses an hour on that cycle you need on the order of 70 to 90 buses in the system. That is a fleet, not a handful of vans.

Where the lots go

The lot belongs on the high-capacity road, before the traffic drops onto the two-lane. A surface lot holds about 110 cars per acre once the drive aisles are counted.

OriginShareCarsLotWhere
St. Lucie35%~6,000~55 acresOff I-95 at SR 714, or on 714 east of 609. Cars never enter 609.
West Palm Beach area35%~6,000~55 acresOff the Turnpike or I-95 south. Bus runs north on Kanner.
Okeechobee20%~3,500~32 acresOn SR 710 northwest of the village, before the rural stretch.
Stuart10%~1,700~16 acresEast of the village on Kanner. Small. Not the priority.

One lot for everyone would be about 160 acres. That is why it is split. Each lot also needs about an acre of bus staging. Each campus gate needs a bus pad and a turnaround, well under an acre, because the cars are not parking there.

What the trip looks like

A St. Lucie worker drives to the 714 lot, parks, and boards. The bus runs 714 to 609 to Warfield and turns into the gate. If the bus is not sitting in a car queue, the ride is 20 to 30 minutes. The worker is on site. The car is 9 miles away, off the two-lane.

At release, the same bus runs the loop in reverse. The evening peak is the same number of buses, not the same number of cars. The 4:00 PM release that currently puts cars on the road until 1:30 AM becomes a bus queue that clears in the time it takes to run the fleet through the gates.

MeasureResult
Vehicles on 609 in the arrival windowBuses only, on the order of 20 to 40 an hour from the St. Lucie lot
Mouth rate neededA bus every minute or two, not 600 cars an hour
Time to clear one campusAbout 2 hours of bus arrivals, if the fleet is sized for it
Car queue on the two-laneNone, if the lots are used
Haul trucksStill on the road. The shuttle does not move concrete.

What has to be true for it to work

  • The lots exist before the first shift, not after the roads fail.
  • The bus is mandatory for the arrival window, or the car count returns.
  • The three campuses share the lots and the fleet. Three separate shuttle plans that do not talk to each other will still stack buses at the same hours.
  • The haul trucks are scheduled outside the bus window, or they share the mouth with the buses and the gain shrinks.
  • Someone pays for the fleet, the drivers, the lots, and the insurance. This is an applicant cost, not a village cost.

Strengths

The only option that takes the private car off the two-lane. Turns a 9.6-hour car drain into a 2-hour bus window. Leaves the through lane for local traffic and EMS. Scales with stagger. Matches what other counties have already required for single projects of this size.

Weaknesses

Land. A 55-acre lot is a project of its own. Fleet. Seventy to ninety buses is a contract, not a phone call. Enforcement. If the lot is optional, it will not be used. The trucks remain. And if the lots are late, the first months of construction run on the do-nothing numbers.

Does it work

Yes, if it is built and required. It is the only scenario in this report where the morning window is long enough and the two-lane is not the parking lot. It does not work as a suggestion. It works as a condition.

Comparison

Side by Side

NothingStaggeredFlaggersTimed lightsShuttle
Mouth rate600 / hour600 / hour~900 / hour~1,100 / hourBuses, not cars
How the line startsFull at 5:00Builds 5:00 to 8:00Full at 5:00Full at 5:00Buses only
Hours to clear one driveway9.6Still past 8:006.45.2~2, if fleet is sized
Queue at 8:00Full lineShorter, still thousandsShorterShorterNone
Fits a morning windowNoNoNoNoYes
WorksNoNoNoNoYes, as a condition

Flaggers and signals make the crossing faster. They do not make 17,256 cars fit on roads that hold a few thousand in queue and empty at under a thousand an hour. The shuttle is the change in kind. Everything else is a change in rate, and the rate never catches the volume.

What the record does not yet show

A cumulative study of all three campuses on one network. A required off-site lot. A shuttle condition. A stagger. A signal plan that counts the feeder queues on 609, 714, and Kanner as part of the load. Until one of those is in the file, the operating case is the first column.