The Traffic

The roads. The Village is allowing an impact on pavement it does not control. State roads, county road, separate permits. The players. FPL and the Tesoro PUD, already approved, with a 7,200 daily cap. Silver Fox 606, PUD withdrawn, now a by-right site plan and a lawsuit. Warfield 18 and Growler, a vested filing with no published trip table. The load. 17,256 worker vehicles. Not in any file. ITE prices a finished building. One morning. Why 600 an hour at the mouth means the first car is in line the night before, and why stagger, flaggers, and signals do not close it. What the plans require. Chapter 6 is street design. The real study is checklist item 23 and Chapter 7 at the Village, and Rule 14-96 at FDOT, on a later clock. Who can still act. FDOT, the county, a consistency challenge. What is not available. The four questions a reader should ask of each file.
Village of Indiantown · Martin County · State Highway System
The Traffic
Three campuses. Two-lane roads the Village does not own. A construction load that is not in any of the files. A walk through who is building, what the plans require, and why the morning does not clear.
The Village Is Allowing an Impact on Pavement It Does Not Control
SR 710 / Warfield, SR 76 / Kanner, and SR 714 are state roads. The Florida Department of Transportation permits every connection to them. CR 609 is a county road. Martin County permits that one. The Village of Indiantown can approve a land use inside its limits. It cannot open the entrance.
That split is the whole story. A Village yes and a road yes are separate acts, by separate governments, under separate rules. One does not bind the other. The three projects are moving as if the land-use file is the traffic file. It is not.
Three Applicants, Three Plan Types
Tesoro Groves, Florida Power & Light. A 5,722-acre PUD, applications RZ-26-002 and SP-26-005, approved by the Village Council on April 30, 2026. It is a framework, not a building. Data centers are among the permitted uses. The traffic number in the file is a cap: 7,200 daily trips, the light-industrial equivalent of about 2 million square feet, for the whole PUD. Every later site plan must bring its own study of the actual use. Access is onto SR 76 / Kanner. FDOT has not been asked for that cut, because no building has been site-planned under the framework yet.
Silver Fox, Silver Fox 606 LLC. Nelson Ferreira and, in the revised proposal, Panattoni. A PUD for 2.2 million square feet was withdrawn on April 29, 2026. The land stayed heavy industrial. The current path is a site plan on that zoning, with a claim that the use is by right. A plat was administratively approved on September 17, 2026. A lawsuit filed in October challenges later Village action and asserts vested rights. Access is Silver Fox Lane to SR 710 / Warfield. The withdrawn PUD had one sentence on traffic: stay inside the thresholds on the master site plan. It stated no trip number. Those thresholds left with the withdrawal.
Project Growler, Warfield 18 LLC. Rory Greenberg. A site plan filed August 19, 2026, for about 600,000 square feet in four buildings on about 146 acres at 18300 SW Warfield Boulevard, the former Florida Steel site. The applicant says the filing is vested to the rules on that date and exempt from a moratorium that is not retroactive. The Village manager has said Growler, Silver Fox, and a third filing, Project Parrot, would continue if the pause is not retroactive. Access is a driveway onto SR 710. No trip table has been published.
| Tesoro / FPL | Silver Fox | Growler | |
|---|---|---|---|
| Instrument | PUD framework, approved | Site plan on existing zoning | Site plan, vesting claim |
| Traffic number in the file | 7,200 daily, whole PUD | None published | None published |
| Entrance | SR 76 / Kanner | Silver Fox Lane to SR 710 | SR 710 / Warfield |
| Who signs the land use | Village Council, done | Village site-plan review | Village site-plan review |
| Who signs the entrance | FDOT | FDOT | FDOT |
What the Files Count, and What They Do Not
Each campus in this record is sized at 6,500 people during construction. At 1.13 people per vehicle, the National Household Travel Survey work-trip rate, that is 5,752 vehicles at each driveway and 17,256 across the three. Add about 1,080 truck trips a day in the concrete peak. The crews do not live in the village. St. Lucie and the West Palm Beach area supply about 35 percent each. Okeechobee about 20. Stuart is thin.
ITE trip generation, the manual FDOT names in Rule 14-96, prices an occupied building. A finished data center generates a fraction of a trip per 1,000 square feet. That is why a 7,200 daily cap looks large against a data-center rate. The manual is counting the building after it opens. It is not counting the people who build it.
The number that is not in any application
5,752 worker vehicles at one mouth. One unsignalized crossing clears about 600 an hour. That is 9 hours and 35 minutes to empty one driveway. The first car has to be in line at 10:25 the night before to be parked by 8:00 AM. Three campuses on the same morning do not fit in a morning.
Why the Line Does Not Clear
Every trip ends at one of three mouths. Silver Fox on Silver Fox Lane. Growler on Warfield. FPL on Kanner. The roads are two lanes. None of the mouths has a signal. A car on the driveway side turns in behind the car ahead. A car on the far side has to cross the opposing lane. That crossing is the limit. One vehicle every 6 seconds is 600 an hour.
CR 609 from SR 714 to Warfield is 9.1 miles. At 18 feet per car it holds about 2,669 cars. The 609 share is about 2,014 vehicles, roughly 6.9 miles of that road. The cars fit. The mouth cannot empty them. At 600 an hour those 2,014 vehicles take 3 hours and 20 minutes just to turn onto Warfield, before they join the line at a gate.
A stagger helps and does not solve it. Spread the arrivals from 5:00 to 8:00 and about 1,900 an hour arrive at a mouth that clears 600. The line at 8:00 is shorter, not gone. Flaggers get the rate to about 900. A temporary signal gets it to about 1,100. Neither fits a morning window. The only change in kind is a shuttle that parks the cars on I-95 and the Turnpike and puts buses on the two-lane. That is a condition. It is not in any of the three files.
Chapter 6 Does Not Count Cars
Village LDR Chapter 6 is titled Traffic and Street Design. It sets right-of-way widths, lane widths, and cul-de-sac length. It does not set a level of service. It does not name ITE. It does not require a study. A project can satisfy Chapter 6 and still fill Warfield.
The study requirement is elsewhere. The Site Plan Checklist, item 23, requires a Traffic Impact Analysis Report, signed and sealed by a Florida engineer. Chapter 7 requires a showing that the project does not drop the adopted level of service: LOS C on these roads, LOS D on the SIS. FDOT Rule 14-96 requires its own study with the connection permit, and names the ITE 11th Edition as the trip method. An Intersection Control Evaluation is required at 4,001 or more daily trips on one connection, or if a signal is proposed.
The Village study is due with the site plan, before a development order. The FDOT study is due when someone asks to cut the state road. A project can leave a Village hearing with an approval and no FDOT study on file. The entrance is not legal until the second study is accepted.
| Requirement | Where it lives | When it is due | What it measures |
|---|---|---|---|
| Street design | LDR Chapter 6 | With the plans | Pavement inside the site |
| Traffic impact analysis | Site-plan checklist, item 23 | With the site plan | Whatever scope the Director set |
| Concurrency | LDR Chapter 7 | Before the development order | LOS C on these roads |
| Connection study | FDOT Rule 14-96 | With the driveway permit | ITE 11th Edition, occupied use |
| Trip cap | Tesoro PUD only | Each later site plan | 7,200 daily, permanent, whole PUD |
The Gates That Stop the First Truck
FDOT can deny a state-road connection, or allow it only with turn lanes, a signal, a construction traffic plan, and a bond. The county can do the same on CR 609, and can require proportionate share if concurrency applies. The Village can condition a site plan: stagger, shuttle, off-site lots, hours. An affected party can challenge a development order under §163.3215 if it is inconsistent with the comprehensive plan.
What is not available is a general veto. Proportionate share, if offered, generally closes a pure concurrency objection. Stuart and St. Lucie do not own these roads and cannot deny the connection in their own chambers. Their route is the record, the FDOT review, and a consistency challenge if their residents or their roads are adversely affected.
The order of gates
Village or county land-use approval. Necessary, not sufficient. FDOT connection permit for every entrance on a state road. County permit for every entrance on CR 609. Right-of-way and maintenance-of-traffic permits before a construction vehicle uses either. Until those are issued, the impact the Village approved has no legal way onto the road.
What a Reader Should Ask
For Tesoro: does the traffic study required with the first real site plan count construction workers, or only the 7,200 permanent trips?
For Silver Fox: what study is in the current site-plan file, now that the PUD thresholds are gone, and does it include the other two campuses?
For Growler: which edition of the LDR is the traffic standard, and does that edition require a cumulative look?
For FDOT, on all three: did the pre-application meeting set a scope that includes the construction peak, the shift hour, and the other projects on the same roads?
Those four questions are the record. They are not in one place, because the plans are not one plan. The players are in three files. The load is on one network. The standards being applied are the standards for the finished building. The load that breaks the road is the one that builds it.